The production schedule
The following entries are extracted from the production schedule. It gives a rough idea of what goes into making a large event happen.
May 1st
Cabins arrive for North Carriage Drive- the vehicle marshalling area.
May 2nd
Boarding/Protection of Canada gate
Phones installed at North Carriage Drive
Show & Event Security commence stewarding & security
First of over 90 generators arrive
First Trackway delivery
May 3rd
First Aid cover commences
Catering tent arrives 25m x 25m
May 4th
Production village cabins arrive
Kitchens arrive
Radio and base station installation
Plumbing installation
Production toilets installation
Telephone line installation starts. First of over 800 lines
Water towers in Green Park
May 5th
Furniture arrives for cabins
Caterers load in
Broadcast boxes construction commences
May 6th
Steelshield erected around production village
May 7th
Catenary rigging down both sides of The Mall
May 8th
Power, sound & lighting cabling starts
May 10th
Stage build commences
May 12th
First staging crane call south stage
May 13th
Second staging crane call north stage
May 17th
Projection tests
May 18th
Traffic cones down the Mall
May 19th
Screen structure build commences
Broadcast edit suite build starts
May 20th
Cable Bridge building starts
Commence camera/media platform build
May 22nd
Mall screen and audio cabling commences
Fit out edit suites
Main stage build completed
May 23rd
Trackway installation for Broadcast areas
Seating installation North & South commences
Cable bridges in Green Park
Tree trusses(LX) on Mall
May 24th
Telecoms fit out of edit suite
Crane for Green Park cable bridges
May 25th
Sound tower build for main stages
May 26th
Dressing room area toilets arrive
Admiralty Arch LX tower build
Cable bridges Constitution Hill
Crane for QVM generator
May 27th
LX install on Mall
LX & Rigging install on Buckingham Palace roof
Screen Platforms in Buckingham Palace forecourt
Signage tower build
Projector towers build
May 28th
Screens install commences
Cabins for Pyro team in Green Park
Choir stand seating install
Fencing for Green Park & St. James’ Park stages
Fencing for Green Park Pyro zone
May 29th
Pyro lifting onto Buckingham Palace roof
Projection install commences
Trackway for Green Park & St. James, Park stages
QVM Beacon structure install commences
LX install on broadcast box roofs
Pyro install Green Park commences
Cladding commences on structures
Fountain feature install
May 30th
Delivery of public toilets
Trailer stage install Green Park & St. James Park
Toilets into Buckingham Palace forecourt
Sound installation north & south stages
Palace forecourt screens install
Observation tower build
May 31st
Trackway & fencing to Hyde Park
LX & Sound install Green Park & St. James Park stages
LX install for QVM
Terraplas install
LX programming
June 1st
Fencing, cabin, stage & screen installation in Trafalgar Square
Screen installation in Hyde Park
June 2nd
Sound & LX install in Trafalgar Square
Screen Install on Horseguards
Mall audio test
Beacon catenary installation
Overnight beacon firing test
St. Pauls screen support
50 Years Parade build on Horseguards
Balcony Hanging installation
Water Sculpture rehearsals
Son et Lumiere rehearsal
June 3rd
Toilet, cabin, fencing and welfare deliveries for all procession form up areas
Crane call Horseguards for Services Parade large vehicles
Clear fencing in Hyde Park after 41 Gun Salute
Main Stage rehearsals after Changing the Guard